A whole-home renovation in Los Angeles typically costs $100 to $500 per square foot of house: about $200,000 to $350,000 to refresh a 2,000-square-foot house cosmetically, $300,000 to $500,000 for a multi-room renovation, and $500,000 to $800,000 to take the same house down to the studs. Moving walls, changing the roof line or touching the foundation pushes it past that. Green Design and Build is a licensed general contractor (CSLB #1110975) based in Van Nuys that designs, permits and builds whole-home renovations for homeowners across Los Angeles County, Orange County, Ventura County, western Riverside County and western San Bernardino County. The figures on this page are typical Los Angeles budgeting ranges, not a quote; your number depends on how much of the house you open, what demolition finds, and the finishes you choose.
We are led by Dekel Sofer; the company has completed hundreds of projects and holds a 4.7-star rating across 146 reviews on Yelp.
Whole-home renovation cost by scope
Whole-house work is priced per square foot of the house, not per square foot of the rooms you are changing. The table gives the range for each level of work and what it comes to on the three house sizes we see most often across the San Fernando Valley and Orange County.
| Level of work | Per sq ft of house | 1,500 sq ft house | 2,000 sq ft house | 2,500 sq ft house |
|---|---|---|---|---|
| Cosmetic refresh, whole house | $100–$175 | $150,000–$260,000 | $200,000–$350,000 | $250,000–$440,000 |
| Multi-room renovation | $150–$250 | $225,000–$375,000 | $300,000–$500,000 | $375,000–$625,000 |
| Full gut to the studs | $250–$400 | $375,000–$600,000 | $500,000–$800,000 | $625,000–$1,000,000 |
| Gut plus structural changes | $350–$500+ | $525,000–$750,000+ | $700,000–$1,000,000+ | $875,000–$1,250,000+ |
How we estimated these numbers
The ranges on this page are budgeting estimates for Southern California, not a price list. They are drawn from Green Design and Build’s own written proposals and completed projects across Los Angeles, Orange, Ventura and western Riverside and San Bernardino counties, checked against current supplier and subcontractor pricing. A real project can come in lower or higher depending on the house, the scope and the finishes. Reviewed by Dekel Sofer, licensed general contractor (CSLB #1110975), September 2026. Publishers and journalists are welcome to cite these figures with a link to this page.
Those ranges include design, engineering, permits, demolition, all trades, materials and finishes at a normal mid-range to upper-mid-range specification. They do not include furniture, landscaping, a pool, a detached structure or the cost of living somewhere else while the work happens.
What you get at each level
Cosmetic refresh, $100 to $175 per square foot
Nothing structural moves and very little plumbing or electrical is rerouted. New flooring throughout, paint inside and out, new interior doors and hardware, new lighting and switches, refinished or replaced kitchen cabinets with new counters, and bathrooms updated in place with the same fixture locations. This is the level where a house stops looking dated without the walls ever coming down, and it is the best value per dollar of the four. For the line items, see our cost guides to hardwood floors, vinyl plank flooring, interior painting and exterior painting.
Multi-room renovation, $150 to $250 per square foot
The kitchen and bathrooms are taken back to the framing and rebuilt, usually with new layouts, while bedrooms and hallways get the cosmetic treatment. Plumbing and electrical are rerouted in the rooms being rebuilt. Most of the whole-house projects we run land here. See our guides to kitchen remodel cost and bathroom remodel cost for what those rooms carry on their own.
Full gut to the studs, $250 to $400 per square foot
Every interior surface comes off. The house is rewired and repiped, the HVAC is replaced, insulation goes in everywhere the walls are open, and the entire interior is rebuilt. On a 1950s to 1970s house this is often the only honest answer, because the wiring, the galvanized supply lines and the single-pane windows all reach the end of their lives at the same time. Layouts can change freely as long as bearing walls stay put.
Gut plus structural changes, $350 to $500 and up
Bearing walls come out and steel or engineered beams go in, the roof line changes, windows are enlarged, or the foundation is repaired or extended. Everything above applies, plus a structural engineer, deeper footings, and a longer plan check. If you are also adding square footage, price that part separately at addition rates; our room addition cost guide covers those.
What changes the price
Two houses of the same size on the same street can be $300,000 apart. When they are, it is one of the items below.
How much of the house you actually open
Drywall is cheap; what is behind it is not. Once a wall is open you are into rewiring, repiping, insulation, and whatever framing repair the inspector wants. Deciding to open one more room is rarely a small decision, and deciding to leave a room closed is the single most effective way to hold a budget down.
Kitchens and bathrooms carry most of the budget
On a typical whole-house project the kitchen and bathrooms are roughly half the money in about a fifth of the floor area. A published kitchen remodel in Los Angeles runs $25,000 to $100,000 on its own, and each full bathroom adds meaningfully on top. If the whole-house number is coming in high, these rooms are where the specification actually moves it.
What demolition finds
Knob-and-tube wiring, galvanized water lines, cast-iron drains at the end of their life, termite damage in the sill plate, a rotted subfloor under a bathroom, an unpermitted addition framed without a header. None of it is visible before demolition, and all of it is common in Valley houses from the 1950s and 1960s. We carry an allowance for it and price the work as it is uncovered, with the framing photographed and shown to you before anything is closed up. If the house already shows signs of foundation movement, get that assessed before the design is finished rather than after demolition.
The electrical service
No code section says a remodel requires a new panel. What forces it is the load calculation: add an induction range, a heat pump, a heat-pump water heater and an EV charger to a 1950s 100-amp service and the calculation fails. In the City of Los Angeles, an electrical service up to 400 amps in an existing residential building qualifies for an express permit with no plan check, so the permitting is straightforward; the cost sits in the panel, the service conductors and the utility coordination for the meter, which runs on its own track alongside the city permit. That work is performed by licensed electrical contractors and scheduled and supervised by us as your general contractor.
The energy code, once the walls are open
The 2025 California Energy Code took effect for permits filed on or after 1 January 2026, and the edition is set by your permit application date. On an alteration it does not ask for everything, but it does ask for specific things once you disturb specific assemblies: walls you open must be insulated to roughly R-15 in a 2×4 cavity or R-21 in a 2×6, altered ceilings go to about R-49 in most Los Angeles-area climate zones, replacement windows must meet current U-factor and solar-heat-gain numbers, and 25 feet or more of new or replaced duct triggers sealing and third-party leakage testing. Altered or replacement heating systems generally may not use electric resistance as the primary heat source. Los Angeles spans several energy-code climate zones, so the exact numbers depend on your address. The full requirements are in the California Energy Commission’s 2025 Single-Family Residential Compliance Manual.
Fire-zone requirements
In a Very High Fire Hazard Severity Zone, the wildland-urban interface requirements are not a new-construction-only code. LADBS applies them to alterations and additions: replacing 50 percent or more of the roof within 12 months means the new roof must meet current standards and achieve a Class A rating, and altering exterior walls, windows, doors, decking or siding pulls that work into compliance too. Ember-resistant vents, ignition-resistant decking and rated glazing are the usual line items. Check your address against the state map and confirm with your building department at permit time, because jurisdictions adopted the 2025 CAL FIRE zone maps on their own schedules. Our roof replacement cost guide covers the roofing side of this in detail.
Finishes, and how late you choose them
The spread between a good stock cabinet and a custom one, or between a porcelain slab and a book-matched natural stone, is easily $80,000 across a whole house. The more expensive problem is timing. Custom cabinets take about three weeks to manufacture after the order is placed, and a decision made after framing is finished usually costs more than the material difference, because it moves the electrical, the plumbing rough-in and the tile crew with it. We settle finishes during design, not during construction.
Do you need permits for a whole-home renovation in Los Angeles?
Yes, and usually four of them. LADBS issues building, electrical, plumbing and mechanical permits separately, and a whole-house project needs all four. The question that matters is which review track you land on. Simple like-for-like work, including a kitchen or bathroom remodel with no structural changes, can go through an express permit with no plan check. The moment you move a bearing wall, change the roof structure or go past 400 amps of electrical service, you are into plan check with stamped drawings.
LADBS does not publish a committed turnaround for regular residential plan check; its own description is that plans are assigned within a few days and returned within weeks depending on workload, with an expedited option available for 50 percent more of the plan check fee. In our experience across Los Angeles-area jurisdictions, plan check on a whole-house remodel runs one to six weeks. There is also an LA-specific trigger worth knowing: the Los Angeles Green Building Code applies to any alteration with a valuation greater than $200,000, which a whole-house renovation almost always exceeds even with no added square footage. Other cities in our service area do not have that valuation trigger.
The four rules that can turn a remodel into a rebuild
This is the part that surprises homeowners, and it is the reason a “we will just keep one wall” plan so often fails. There is no single definition of a major remodel in Los Angeles. There are four separate percentage tests in four different bodies of law, and a gut remodel can trip them independently. Cross one and your existing house stops being grandfathered and starts being measured against today’s rules.
| Test | Threshold | What crossing it triggers |
|---|---|---|
| Zoning floor-area documentation | Demolishing more than 50% of perimeter exterior walls and more than 50% of the roof, or adding more than 1,000 sq ft | Full as-built architectural and engineering plans; the house is measured against current floor-area ratio, height and setback rules |
| Legal nonconforming status (LAMC 12.23) | Retaining less than 50% of the perimeter wall length of the nonconforming portion | Loss of the grandfathered setback or yard; the rebuilt house must meet today’s setbacks |
| Hillside major remodel (LAMC 12.03) | Alterations worth more than 50% of the building’s replacement cost within any one-year period | Baseline Hillside Ordinance standards: slope-based floor area, height limits, grading caps, street dedication |
| Building code alteration level (California Existing Building Code) | Work area exceeding 50% of the aggregate building area | Level 3 requirements that reach beyond the work area: egress, fire protection, structural and building services |
The hillside test is a value test rather than a wall-percentage test, and it aggregates over a rolling year, so phasing the project across two winters does not avoid it. The nonconforming rule is the one that catches the most people: a 1930s house sitting in what is now the side-yard setback keeps that position only if you keep half the perimeter wall length of the nonconforming portion. Gut it past that line and the new house has to sit where today’s code says it can. The restoration allowance in the same section is capped at 75 percent of replacement value. You can read the section itself in LAMC 12.23.
Also check ZIMAS for overlays before you pay for drawings. A Historic Preservation Overlay Zone means most exterior changes need Planning approval and significant changes can be under review for up to 75 days. In the Coastal Zone the thresholds are far tighter than anywhere else in the city: a coastal development permit is required once internal floor area increases by 10 percent or height increases by 10 percent, and the single-family improvement exemption itself depends on retaining 50 percent or more of the existing exterior walls.
Asbestos and lead: the step before demolition
On any house built before about 1990, an asbestos survey sits on the critical path before demolition starts, and it is a regional rule that covers Los Angeles, Orange, Riverside and San Bernardino counties. Under South Coast AQMD Rule 1403, a survey report signed by a Certified Asbestos Consultant is required before any demolition or renovation, with a narrow exception for single-unit dwellings where less than 100 square feet of intact material is disturbed. Removing more than 100 square feet of material containing more than 1 percent asbestos requires notification 10 working days ahead, and only contractors on the Cal/OSHA asbestos registration may do the removal. A whole-house project clears those thresholds easily, so build the survey and the notification window into the schedule rather than discovering them the week demolition was supposed to start.
Lead is the second one. Houses built before 1978 fall under the federal Renovation, Repair and Painting rule, which requires the firm doing the work to be certified and to use certified renovators following specific containment practices. A whole-house remodel of a pre-1978 house will exceed any plausible threshold, so ask any contractor bidding your project to show you their certification. It is a fair question and a licensed firm will not mind it.
How long does a whole-home renovation take?
Plan on two to five months of construction, plus roughly one to three months of design and permitting before anyone swings a hammer. The design and permitting stage is the one homeowners consistently underestimate.
| Phase | Typical duration | What happens |
|---|---|---|
| Feasibility and site assessment | 2–4 weeks | Site visit, measurements, zoning and overlay check, scope and budget alignment |
| Design and engineering | 10–20 days | Plans, structural engineering where walls move, energy compliance documents, 3D rendering |
| Plan check | 1–6 weeks | City review and corrections; longer with hillside, coastal or historic review |
| Construction | 2–4 months typical, up to 5 on a full gut | Demolition, rough trades and inspections, insulation, drywall, cabinets, tile, finishes |
| Close-out | 1–4 weeks | Final inspections, punch list, cleaning, handover |
Two things stretch a schedule more than anything else: decisions made late, and long-lead materials ordered late. Custom cabinets alone take about three weeks to manufacture. We approve a 3D rendering before demolition starts precisely so the layout and the finish list are settled while changing them is still free.
Should you move out?
For a full gut, yes. There is no functioning kitchen, the bathrooms are out, the power is off in sections, and the dust from demolition goes everywhere regardless of containment. Most families move out for the two to five months of construction, and that housing cost belongs in the project budget from the start, not as a surprise in month two.
The alternative is a phased, room-by-room renovation where you keep a working kitchen or bathroom while the other half of the house is under construction. Phasing typically runs two to five months as well, and it is genuinely the right answer for some households, but it is not cheaper. Crews mobilise more than once, temporary partitions and protection get built and rebuilt, and the trades cannot run their rough-in in one continuous pass. Decide this before design, because it changes how the drawings are sequenced.
A real whole-home remodel in Encino


The Encino project is a good illustration of what a multi-room renovation actually involves. The interior was stripped back to framing so the electrical and plumbing could be rerouted for new layouts in the kitchen and both bathrooms, and the subfloor and framing were repaired where demolition exposed problems, before anything went back in. The kitchen was rebuilt with white shaker cabinets, a marble-look tile backsplash and a dark island wrapped in a quartz waterfall top; the primary bath went to large-format black marble-look slabs with a floating fluted vanity, the second bath to a double vanity with backlit mirrors; the living room fireplace was rebuilt as a full-height stone surround with a slat-wood wall that hides the television wiring. New flooring and doors ran throughout.
The sequence matters more than any single finish. Cabinets were set first, then counters templated to the installed cabinets, then tile. Doing it in that order is why the backsplash meets the counter cleanly. Photographs of every stage are on the Encino whole-home remodel project page.
What actually pays you back at resale
If part of the reason for the project is resale value, the pattern in the data is consistent and slightly counterintuitive: modest exterior and mid-range work recoups far more than large upscale interior work. The figures below are the Los Angeles market rows from the 2025 Cost vs. Value Report, which is an industry survey rather than a government dataset, and which reports averages across the metro rather than your street.
| Project (Los Angeles, 2025 report) | Job cost | Resale value | Cost recouped |
|---|---|---|---|
| Siding replacement, fiber-cement | $21,879 | $28,030 | 128.1% |
| Minor kitchen remodel, midrange | $29,765 | $37,768 | 126.9% |
| Bath remodel, midrange | $27,143 | $24,312 | 89.6% |
| Window replacement, vinyl | $23,783 | $19,799 | 83.2% |
| Roofing replacement, asphalt | $36,417 | $26,804 | 73.6% |
| Major kitchen remodel, midrange | $86,214 | $49,079 | 56.9% |
| Bath remodel, upscale | $85,055 | $35,982 | 42.3% |
| Major kitchen remodel, upscale | $171,369 | $65,023 | 37.9% |
| Primary suite addition, midrange | $182,518 | $58,271 | 31.9% |
These are typical Los Angeles budgeting estimates, not a price list or a quote. Your project can come in lower or higher depending on the house, the scope and the finishes; the only real number is a written proposal after a site visit.
The practical reading: a whole-home renovation is mostly a decision about how you want to live, not an investment that returns its cost. If resale is the driver, the money goes furthest on the envelope and on mid-range kitchens and baths. If you are staying ten years, spend where you will notice it every day and ignore the percentages.
How to compare whole-home renovation quotes
Quotes for a whole house are only comparable when they describe the same scope, and on projects this size the differences are usually hidden in what is left out. Check that each proposal states, line by line: which rooms are taken to the studs and which are cosmetic; whether design, structural engineering and energy compliance documents are included or billed separately; the permit and plan check fees, and who pays for corrections; the asbestos survey and any abatement; a named allowance for concealed conditions found at demolition, and the unit price beyond it; the actual cabinet line, counter material and tile allowances rather than the word “standard”; whether appliances, light fixtures and plumbing fixtures are supplied or owner-provided; the electrical service size the price assumes; temporary protection, dust containment and debris disposal; and the warranty.
Then check the contract terms, because California sets rules here and they are worth knowing. Under the CSLB home improvement contract rules, the down payment on a home improvement contract may not exceed $1,000 or 10 percent of the contract price, whichever is less; payments may not run ahead of the value of work performed; and you have three business days to cancel, or five if the buyer is 65 or older. Verify the license itself on the CSLB website, with workers’ compensation on file. A contractor asking for a third of the job up front is telling you something about how they are funded. Our guide on how to hire a general contractor without getting scammed goes through the rest of the red flags, and what a Los Angeles general contractor costs explains how overhead and management fit into a number like this.
Where we do whole-home renovations
We run whole-home renovations from our Van Nuys office across the San Fernando Valley, the rest of Los Angeles County, Orange County, Ventura County, western Riverside County and western San Bernardino County. The work changes with the housing stock. Valley ranch houses from the 1950s and 1960s usually need rewiring, repiping and a wall taken out between the kitchen and the dining room. Post-war Orange County tracts tend to be cosmetic refreshes with one reconfigured bathroom. Hillside houses in the Santa Monica Mountains and the canyons bring the hillside ordinance, fire-zone materials and access constraints with them. Spanish and Mediterranean houses in Pasadena and the Inland Empire come with tile roofs and plaster that reward keeping rather than replacing. See all of our service areas, or read more about our full home renovation service.
Whole-home renovation cost FAQs
How much does it cost to renovate a whole house in Los Angeles?
About $100 to $500 per square foot of house, depending on how deep the work goes. On a 2,000-square-foot house that is roughly $200,000 to $350,000 for a whole-house cosmetic refresh, $300,000 to $500,000 for a multi-room renovation with the kitchen and bathrooms rebuilt, $500,000 to $800,000 for a full gut to the studs, and $700,000 and up when bearing walls, the roof line or the foundation change. These are typical Los Angeles budgeting ranges, not a quote.
Is it cheaper to renovate or to tear down and rebuild?
Renovating is usually cheaper as long as you stay on the right side of the thresholds that trigger full current-code compliance. Once a project demolishes more than half the perimeter walls and more than half the roof, it needs full as-built plans and is measured against today’s floor-area, height and setback rules, and it may forfeit a grandfathered setback. At that point the cost gap between a deep remodel and new construction narrows considerably, and rebuilding can buy you a better plan for similar money. The test is worth running early, during feasibility, not after demolition.
How long does a whole-house renovation take?
Two to five months of construction, plus about one to three months of design and permitting first. Within that: feasibility and site assessment two to four weeks, design and engineering 10 to 20 days, plan check one to six weeks, construction two to four months for most projects and up to five for a full gut, and close-out one to four weeks. Hillside, coastal or historic review adds time at the plan check stage.
Do I need to move out during a whole-home renovation?
For a full gut, effectively yes; most families move out for the two to five months of construction, and that housing cost should be in the budget from the start. A phased room-by-room renovation lets you stay, and also runs about two to five months, but it costs more rather than less because crews mobilise repeatedly and the trades cannot run their rough-in in one pass.
Do I need permits to renovate my whole house in Los Angeles?
Yes. LADBS issues building, electrical, plumbing and mechanical permits separately and a whole-house project needs all four. Like-for-like work with no structural changes can go through an express permit with no plan check; moving a bearing wall, changing the roof structure or exceeding 400 amps of electrical service moves the project into plan check with stamped drawings. In the City of Los Angeles, any alteration valued above $200,000 also falls under the Los Angeles Green Building Code, which a whole-house renovation almost always does.
Does a whole-house remodel require solar panels?
No. Under the California Energy Code, mandatory solar photovoltaic and battery storage apply to new construction, not to alterations or additions to an existing single-family house. A remodel, even a complete gut, does not trigger a solar requirement. It does trigger the alteration requirements: insulation in walls you open, current window performance on replacements, duct sealing and testing, and limits on electric-resistance heating.
Which renovations add the most value in Los Angeles?
According to the 2025 Cost vs. Value Report for the Los Angeles market, fiber-cement siding replacement recoups about 128 percent of its cost and a minor midrange kitchen remodel about 127 percent, while a midrange bath remodel recoups about 90 percent, a major midrange kitchen about 57 percent, and a midrange primary suite addition about 32 percent. The pattern is that modest exterior and mid-range interior work returns more than large upscale projects. These are metro-wide survey averages, not a valuation of your house.
How much should I pay before work starts?
On a California home improvement contract, no more than $1,000 or 10 percent of the contract price, whichever is less. After that, payments follow a written schedule tied to work actually completed, and a payment may not exceed the value of the work performed. A request for a large percentage up front on a project of this size is a reason to slow down and ask how the contractor is funding your job.
Get a written price for your whole-home renovation
We will walk the house, check the zoning, overlays and fire-zone status for your address, look at the panel, the plumbing and the framing where we can see it, and talk through which rooms genuinely need to be opened before we write a number. The site visit takes about two hours, the written proposal follows within 48 hours, and it is itemized by room and by trade rather than given as one figure. Design, engineering, permits and construction run under one contract with one project manager. The site visit and the estimate are free, and we reply within one business day.